browser icon
You are using an insecure version of your web browser. Please update your browser!
Using an outdated browser makes your computer unsafe. For a safer, faster, more enjoyable user experience, please update your browser today or try a newer browser.

Workshop Addition

The building of my new workshop

Final Inspections Tomorrow…

Tomorrow is the final electrical/plumbing inspection. Provided everything passes, I plan to begin work on the interior on Sunday. (My wife’s birthday is Saturday so I’m taking the kids while she has a “spa day”.) I’ve been reading “the Workbench Book” by Scott Landis and plan to read Ron Schleining’s “The Workbench” based on recommendations … Continue reading »

Categories: Workshop Addition | Tags: , , | Leave a comment

If These Walls Could Talk…

I spent this past weekend installing Knotty Pine tongue and groove paneling in the new woodshop. As with the floors, I cut costs on materials by purchasing the “value line” stuff (offcuts, etc.) However, unlike the flooring, this stuff was awesome! When they said that most of the pieces were 3′ – 8′ long, they … Continue reading »

Categories: Workshop Addition | Tags: , , , | Leave a comment

I’m Floored!

It was a very busy Labor Day weekend. On Saturday I began the process of installing 300sq ft. of “utility grade” Oak hardwood flooring from Lumber Liquidators. This stuff is only $.89 sq. ft. — and for good reason. Much of it was under 10″ in length (many pieces significantly less). There were numerous pieces … Continue reading »

Categories: Workshop Addition | Tags: , , , | Leave a comment

New Time-lapse Uploaded

I’ve finished editing revision 6 of the time-lapse. Still some more to go, but this seemed like a good point to share.

Categories: Workshop Addition | Tags: , , | Leave a comment

Ready…Set…

…wait a bit longer. Initial inspections were completed last week — electrical, plumbing, insulation, house-wrap, etc. This week the crew finished the rest of the siding. Yesterday the drywallers came in and hung the sheet rock ceiling. On Monday, my order of pine 8″ T&G siding for the interior walls arrived, and I picked up … Continue reading »

Categories: Workshop Addition | Tags: | Leave a comment

Test for Echo

A couple quad boxes with 1.25″ PVC run into the crawl space Before the celing is installed (later this week?) I decided to install some PVC and low-voltage quad boxes to act as conduit for speaker wire, RG-6 and cat5e cabling. The plan is to install 2 sets of 6.25″ speakers in the ceiling — … Continue reading »

Categories: Workshop Addition | Tags: , , , | Leave a comment

Construction Time-lapse Video

Here’s the most current construction time-lapse video. So far we cover groundbreaking through roofing. The trades were here today installing plumbing and electric. We’re closing in!

Categories: Workshop Addition | Tags: , , | Leave a comment

Time-lapse Cameras

Here’s my first post of the developing construction process time-lapse video. I started with a single camera mounted in a tree facing the back of the addition. It worked, but was a bit tighter of a shot than I would have preferred. I kept the camera here through the foundation dig and pour and the … Continue reading »

Categories: Workshop Addition | Tags: , , , | Leave a comment

Blueprints

Thought I’d post a scanned view of the groundplan. The drawings are too large to scan them all in, but I needed this section to make some notes, so I thought I’d post the scan.

Categories: Workshop Addition | Tags: , | Leave a comment

New Shop Construction

For the past couple months we’ve been planning an addition to the house that would become my new woodshop. The prime motivation for this is so that we can reclaim the garage for things like, oh, I dunno – cars, bikes, kid toys, etc. There’s also the issue of the large amount of sawdust covering … Continue reading »

Categories: Workshop Addition | Tags: , , | Leave a comment